Remedial work – Torquay

Harbour Render Systems Ltd were brought in by Bouygues Uk to attend to a problem on an apartment building in Torquay. The building was suffering from water ingress around the patio doors at each balcony level. The doors needed removing, which meant extensive damage to the render around them.

SAS (Europe) Ltd from Devon created a specification that would require mineral fibre bands to be adhesively and mechanically fixed around the doorway and render to be applied to create a feature band around the openings.

The bands are being rendered with the SAS polymer base coat and silicone topcoat.

Harbour Render Systems are continuing to work on this project until September 2019. Approximately 4 balconies are being repaired per week.